      Transforming the San Antonio Canal Waterfront

      P3 and the PRCCDA Navy Pier Redevelopment Project
      (Investment Portfolio for Growth Program (IPG)

       

      PRCCDA NAVY PIER CHALLENGE
      PLEXOS’ STRATEGY, EXECUTION & IMPACT

       
      PRCCDA NAVY PIER CHALLENGE

      Public-Private Partnership (P3)
      Funding available for large-scale commercial and industrial development across a broad set of economic revitalization initiatives

      Magnitude
      Aging infrastructure, loss of economic development, and declining use of public spaces

      Critical Need
      Promote sustainable economic development, improve connectivity, and expand social services

       

       
      Improvements to Fernández Juncos
      Avenue and Connectors

      Traffic reconfiguration, bikeways, sidewalks, crossings, bus stops, and urban design upgrades

      60% design submitted •Design budget: $1.55M

       
      Improvements to Pedestrian Access

      Pedestrian bridges, ramps, crosswalks, walkways, landscaping, lighting, and gathering spaces used as connectors

      Completed 60% design

      Design budget: $442,144

      Anticipated construction bid May 2026

      Anticipated construction award June 2026

      Accelerating Progress Islandwide

      PRDOH City Revitalization Program

       

      PRDOH CRP CHALLENGE
      PLEXOS’ STRATEGY, EXECUTION & IMPACT
       
      Overview

      Provides $1.3B to Puerto Rico’s 78 municipalities to rejuvenate urban centers, downtown areas, and community corridors

      Magnitude
      Repeated infrastructure damage since 2017 from hurricanes, earthquakes, and power grid failure

      Critical Need
      Accelerate islandwide infrastructure, public space, and economic development projects to promote long-term resilience and bring people back to the island

       
      Overview

      Provides $1.3B to Puerto Rico’s 78 municipalities to rejuvenate urban centers, downtown areas, and community corridors

      Magnitude
      Repeated infrastructure damage since 2017 from hurricanes, earthquakes, and power grid failure

      Critical Need
      Accelerate islandwide infrastructure, public space, and economic development projects to promote long-term resilience and bring people back to the island

       
      70 CRP projects developed and approved, representing a total program value of $355.9M

      Facilitated over 1,500 technical assistance, regular meetings, and training events

      Performed compliance and financial reviews of nearly 1,400 invoices submitted by subrecipients to support accurate reimbursement and adherence to program requirements

      Supported municipalities throughout the environmental review process to advance projects toward HUD Authority to Use Grant Funds. To date, 46 of 70 projects have completed the Environmental Review Record, and 50% of the portfolio received AUGF approval

       

      Assisted municipalities with design and procurement activities, resulting in the publication of 59 construction Invitations for Bids across 42 projects, while advancing design development with 66% of projects reaching the 90% design stage

      Refocusing program management services from pre-design to construction•Managed 21 active construction projects totaling $170.4M.

      Assisted subrecipients in the submission of 48 construction change orders to support project implementation and contract administration

      Increasing Energy Reliability for Puerto Ricans

      PRDOH Community Energy and Water Resilience Initiative (CEWRI)

       

      PRDOH CEWRI CHALLENGE
      PLEXOS’ STRATEGY, EXECUTION & IMPACT
       

      Overview
      Provides $350M aimed at increasing resilience against power outages.

      Magnitude
      Systemwide collapse of the electric grid in 2017 post, the largest in U.S. history, infrastructure damage repeatedly since 2017 from hurricanes, earthquakes, and power grid failure.

      Critical Need
      Private backup systems through renewable solar energy equipment (Photovoltaic Systems and Battery Storage Systems).

       

      Key Deliverables

      Funded: 4,918 projects at $115,209,068

      Applications/eligibility completed: 5,472

      Award notifications issued: 4,977

      Contractor companies approved: 105

      Complaints/reconsiderations: 550Outreach / training events: 6

      Intake Centers Set Up/Managed: Caguas, Fajardo, Yabucoa, Orocovis

       

       

      Administrative Closeout

      Submitted for closeout: 4,576

      Approved and closed: 3,337

      Disbursed: $90.3M

       

      Environmental Milestones

      Environmental reviews completed: 5,219

      Site visits completed: 5,219

      Packages reviewed by QC: 5,237

      Packages executed by PRDOH: 5,219

      SHPO consultation: 2,585

       

       

       

      Financial Achievements

      Payments processed: 4,590 at $99.7M Payments approved: 4,574 at $11.1M

       

      Environmental Milestones

      Award disbursements reviewed: 4,622

      System validation performed: 4,596